Home
In this section of the website, we will keep you up to date on the progress of the Leeds Flood Alleviation Scheme phase 2 (FAS2) throughout the construction of the engineering works.
You can find out more information on the scheme on our Leeds FAS2 General Information page.
We have split the Leeds FAS2 into 12 zones which are shown on the below map:
You can navigate to information on each zone from the map or read through zone by zone below.
Overview
Works in zone 10 stretch from the north of Leeds City Station to Wellington Road.
There were no existing flood defences in this area prior to Leeds FAS2.
The works in this zone are now largely complete, with only some minor works on outfalls, and vegetation growth remaining.
The works consist of masonry clad reinforced concrete, and exposed steel sheet pile flood defence walls up to 1.2 metres in height with the latter to be later incorporated into developers’ landscaping works.
As part of the environmental enhancement and mitigation to be provided by the scheme, floating riverbanks have been installed, by No.1 Whitehall Riverside. These installations are floating ecosystems, softening the riverbank wall, as well as providing a habitat for plants and wildlife.
Page last updated 29/2/24
Overview
Works in zone 11a and 11b stretch from Wellington Road to Viaduct Road. This stretch of riverbank is occupied by several businesses including factories, offices, and warehouses along the Kirkstall Road corridor. It also contains the site where our project offices are based.
Works In this location involve raising the level of the left riverbank and constructing a combination of reinforced concrete walls, cladded with brick, and installing steel sheet piles.
Some of the flood defences will be set back from the river to allow for future riverside access.
In a location adjacent to eChem we are constructing a sheet piled wall in the river channel to defend the business against flooding.
At Burley Bridge Mills it is not possible to work inside the building to strengthen the riverside elevation so this will be done by working externally from the river channel.
We are also carrying out work to around a hundred openings in the existing river side wall that are either live drainage outfalls or redundant historical outfalls so that they are sealed against raised river levels.
Works here are part funded by the European Regional Development Fund.
Construction in Zone 11 is ongoing but will not be complete until the end of the project in 2024, as our project offices currently occupy the footprint of one of the planned interventions.
Completed Works
The vegetated reinforced earth embankment at the Tannery site
Sheet piling adjacent to eChem with planting at the foot of the piles and space for planting at the top
Completed works at the HFH site
Completed flood wall at the former Studio 81 site
Completed flood defences at NIC Services
Completed flood defence wall at our former site compound on Viaduct Road
Page last updated 27/3/24
Zone 12a focuses on Armley Mills, which historically served as one of the world’s largest woollen mills and is now the site of Leeds Industrial Museum.
Overview
Armley Mills has historically been impacted by floods and experiences low level flooding every three to five years. Recent large-scale flooding (including the 2015 Boxing Day floods) has resulted in significant issues, including loss of power and long-term damage to historic areas and exhibits.
The works being delivered at Armley Mills are:
Below you can see an artist's impression of how the two flow control structures will look:
Flood defence work at Armley Mills is expected to complete in early 2024.
Completed Works
Installation of the Milford Place Pipe Bridge
Current and upcoming works
Progress on flood walls behind the drying shed
Page last updated 27/3/24
Overview
Works in zone 12b include building concrete flood defence walls cladded with material appropriate for the area.
This area contains Cardigan Fields Leisure Park, where our flood defence works are sensitively being incorporated into a new public realm design, while keeping the new children’s play area. In the below before and after slider, you can see how the site looks as of January 2022:
Completed works
Raised planters at Cardigan Fields made using 3D printed concrete
Flood wall near to Evanston Avenue
Completed works at Kirkstall Viaduct
Page last updated 29/2/24
Overview
Works in zone 12c run further along Kirkstall Road, behind ASDA and the Home Office Site. We will build flood defence walls, plant more trees and create two flow control structures across the goit upstream and downstream of the Home Office as well as a new pumping station.
The flow control structures will have a penstock which will be operated in a flood event to restrict the flow entering the goit.
Work has already started and will complete in early 2024.
Completed works
Completed flood walls at the substation off Redcote Lane
Completed walls and glass panels at Airedale House
Current and upcoming works
Completed pipe works at the pumping station behind the Home Office
Page last updated 27/3/24
Overview
In zone 12d, flood defences will line the left and right bank of the river along the railway line and the Leeds Rhinos Rugby Club training ground.
Access to the river from the Canoe Club will be upgraded with a new canoe ramp and platform which can be used by the public to enjoy the use of the river.
Continuing down the left bank, the flood defence will continue into the old Saint Anne’s Mill area with the public footpath leading around the river being maintained for public use. On the right bank of the flood defence at Saint Anne’s Mill is Kirkstall Valley Nature Reserve which isn’t included as part of the flood defence scheme, but is subject to further funding proposals in the future to enhance the area including creating new footpaths to improve access.
Construction started in summer 2021 and is aimed to be complete by Spring 2024.
Completed works
Completed sheet piling by Kirkstall Training Ground
Current and upcoming works
Page last updated 27/3/24
Zone 13 covers Kirkstall Bridge along with the Kirkstall Bridge Inn and Kirkstall Bridge Retail Park, up through Kirkstall Meadows, Kirkstall Abbey up to Newlay Bridge, this area has a mixture of uses, for business, retail, leisure and areas of significant historical importance.
Overview
In zone 13a on the left bank, our works will replace the flood defence wall, reinstate the gardens and block underground seepage paths at the Kirkstall Bridge Inn which was impacted by the floods on Boxing Day 2015.
Works are also to be conducted in Kirkstall Meadows. We will be making landscape and ecological enhancements across 2.4 hectares including the creation of wetland scrapes and a kingfisher and sandmartin bank. It is currently planned that the wetland habitat will be inaccessible to the public to minimise disturbance. The existing sports pitches will be retained.
The flood defence within this area consist of an embankment that runs along the back of Kirkstall Meadows to protect the railway line, the new embankment will tie into new walls that extend up to the existing Kirkstall bridge.
No flood defence works are proposed for Kirkstall Forge as part of this scheme.
Completed works
Completed works at the Kirkstall Bridge Inn
Current and upcoming works
Works to Kirkstall ramp
Page last updated 27/3/24
Overview
Kirkstall Abbey is classified as a Scheduled Monument, which legally protects it against unauthorised change. Fortunately, the ground height of the Abbey is above the threshold for any flood alleviation works, and there are minimal works being undertaken within the Kirkstall Abbey conservation area as a result of this scheme, although more significant works are being undertaken in the surrounding areas.
We are planning to build a new control structure across the entrance of the goit and in front of Kirkabbey Sluice Gates which will tie into the listed weir. This will limit the volume of water during high river level conditions. This has been designed to ensure that the structure complements the sensitive historic environment in which it is situated, and the existing sluice gates and gate house will be retained. The structure will also be a walkway that could provide additional amenity facilities for visitors to the site and potentially open up new views.
These works will also facilitate the ability for the community aspiration to improve the flow of the goit in this area.
Completed works
Current and upcoming works
New flow control structure at the inlet of Kirkstall Goit
Page last updated 27/3/24
Overview
There will be a combination of remedial building works, flood defence walls and sheet piling which will be clad in stone, so it is in keeping with the conservation area. Works will also be sympathetically undertaken due to the listed bridge in Newlay, in line with the Listed Building Consent.
Completed works
Current and upcoming works
Works on the flood defence walls in Newlay
Page last updated 27/3/24
Overview
Between the Horsforth Vale housing development and Cragg Wood, we are building a flood storage area. This will play an integral part in increasing the standard of protection downstream in Leeds to 1-in-200 years, including an allowance for climate change.
The flood storage area will be operated by a flood control structure consisting of two large floodgates and a 200m embankment with a maximum height of 6.2m above existing ground level. This structure will operate automatically to reduce the volume of river water heading downstream in flood conditions over the 1 in 100-year threshold. The flood storage area can hold up to 1,800,000m3 of water when the river levels are high and then slowly release it back into the river when it is safe to do so.
The below mock ups show how the completed storage area will look before and during a flooding event:
The below video showcases how the storage area will work during high river levels:
The flood storage location is mostly rural, with areas of woodland to the north and south. As part of our work, we will create habitat and wildlife areas in the surrounding area.
Completion of the structure and embankments either side is expected for Spring 2024.
Completed Works
Current and upcoming worksWorks to the embankment at the flood storage area
Page last updated 27/3/24
Overview
Our work at Apperley Bridge will include engineered flood defences downstream from the entrance at Bottom Farm to Woodhouse Grove School. Our works will include flood walls, embankments and a pumping station. Minor works are required on Carr Beck to ensure that we do not increase flood risk to the area.
An artist's impression of how a flood defence wall on Apperley Road will look
Planning was approved in May 2021, construction began in 2022 and is aimed to be complete in Spring 2024.
Completed works:
The reopened Grade II listed Apperley Lane Bridge
The reinstated section of Apperley Road by the George and Dragon pub
Current and upcoming works:
Page last updated 28/3/24
In order to link the drainage network to the new pumping station by the George and Dragon pub, we will need to manage traffic around Apperley Road and Harrogate Road. The majority of the drainage work will be beneath ground level in the pub car park, along Apperley Road, across Harrogate Road and into Parkin Lane. There will be a small adjacent kiosk above ground in the pub car park, which will contain electrical control equipment.
We will be undertaking a phased approach, where the road layout will change over a six month period to enable our works. Here is a summary of key dates:
Phase/event | Status/ Dates |
Reopening of Apperley Lane Bridge | Complete |
Closure of Apperley Road between Apperley Lane Bridge and Harrogate Road Bridge | Complete |
Phase 1 | Complete |
Phase 2 | Complete |
Phase 3 | Complete |
Phase 4 | Complete |
Phase 5 | 29 March (expected) |
Reinstatement works adjacent to the George & Dragon | Complete |
Reopening of Apperley Road | Complete |
Completion of pumping station | Late April 2024 |
More detail of each phase of works is included below.
While some disruption is inevitable, we are minimising this as far as possible and are working closely with the local highway authority.
The constrained nature of the area and complex nature of the works mean that some changes to the dates or details are likely. If this happens, we will update the community of any significant changes in advance, and keep this webpage up to date.
We apologise for the inconvenience this may cause over the next few months, and thank you in advance for your patience.
Works to Date (22/3/24)
On Thursday 24 August, we successfully reopened the listed Apperley Lane bridge to all road users, marking the start of the complex sequence of drainage works across Apperley Road, Harrogate Road, Parkin Lane, and Waterloo Crescent.
The reopening of the bridge meant we could begin works on the drainage and flood defence wall along the small section of Apperley Road between Apperley Lane bridge and Harrogate Road bridge. In order to retain access to the George & Dragon car park, we created a new access point to the west of the existing one. Traffic between Apperley Lane bridge, Apperley Road and the car park is being managed by a three-way traffic light system. This arrangement will be in place until this section of Apperley Road is reopened in February 2024.
We are undertaking a phased approach to the drainage works, the phases now complete are: